Italchemical Industriale
ITALY
Liquid PAC 18
Know-how, Basic and Detail Engineering, equipment procurement, plant erection supervision, commissioning and start up
Capacity
40.000 tpy
Year
1997
Home » References
We’ve delivered turnkey coagulant production plants around the world—tailored to each client’s performance goals.
Know-how, Basic and Detail Engineering, equipment procurement, plant erection supervision, commissioning and start up
40.000 tpy
1997
Know-how, Basic and Detail Engineering
80.000 tpy PAC 18; PAC 10HB
1998
4/16m3
Know-how, Basic and Detail Engineering, equipment procurement, plant erection supervision, commissioning and start up
22.000 tpy
2001
Nozzles drying tower
Revamping of liquid PAC plant, equipment procurement, plant erection supervision, commissioning and start up
40.000 tpy
2/16m3
2002/2007/2008
EP Know-how, basic and detail engineering, equipment procurement, plant erection supervision, commissioning and start up
83.000 tpy PAC 18;
2003
4/16m3
Know-how, detailed engineering, plant erection supervision, commissioning and start up
Know-how, Basic Engineering, Test run
24.000 tpy liquid PAC 18; PAC 10HB
12.000 tpy solid PAC
2004
3/8 m3
Know-how, basic and detailed engineering, plant erection supervision, commissioning and start up
Know-how, Basic Engineering, Test run
24.000 tpy liquid PAC 18; PAC 10HB
12.000 tpy solid PAC
2006
3/8 m3
Know-how, basic and detailed engineering, plant erection supervision, commissioning and start up
Know-how, Basic Engineering, Test run
24.000 tpy liquid PAC 18; PAC 10HB
12.000 tpy solid PAC
2007
3/8 m3
Know-how, basic engineering
40.000 tpy
2008
2/16 m3
EP Know-how, Basic and Detail Engineering, equipment procurement, plant erection supervision, commissioning and start up
80.000 tpy PAC 18% – 130.000 tpy PAC 10HB
start up January 2010
4/16 m3
EP basic and detail engineering, equipment procurement, plant erection supervision, commissioning and start up
40.000 tpy PAC 18% – 70.000 tpy PAC 10HB
ACH plant 7000 tpy
The project is started June 2011
2/16 m3
EP Know-how, basic and detail engineering, equipment procurement, plant erection supervision, commissioning and start up
80.000 tpy PAC 18
The project is started october 2012
2/16 m3
Know-how, basic and detail engineering, plant erection supervision, commissioning and start up
40.000 tpy PAC 18; PAC 10HB
The project is started july 2014
2/16 m3
Know-how, Basic and Detail Engineering, plant erection supervision, commissioning and start up
40.000 tpy PAC 18;
The project is started November 2015
2/16 m3
Know-how, basic and detailed engineering, plant erection supervision, commissioning and start up
15.000 tpy PAC 18
The project is started January 2018
2/6.2 m3
Technology, Basic Engineering, plant erection supervision, commissioning and start up
24.000 tpy
The project is started january 2019
Spry Drier type FSD
EPC turnkey system
40.000 tpy PAC 18;
The project is started November 2019
2/16 m3
Technology, basic and detail engineering, plant erection supervision, commissioning and start up
The project will be complete in 2021
Know-how, basic and detailed engineering
Know-how, basic engineering,
40.000 tpy liquid PAC 18; PAC 10HB
24.000 tpy solid PAC
2021
2/16 m3
Know-how, basic and detailed engineering, plant erection supervision, commissioning and start up
20.000 tpy PAC 18
The project started 2021/2022
2/8 m3
Know-how, basic and detailed engineering, plant erection supervision, commissioning and start up
40.000 tpy PAC 18
The project started in january 2023
2/16 m3
Know-how, basic engineering, commissioning and start up
15.000 tpy PAC 18
The project is started october 2023
2/6.2 m3
Know-how, basic and detailed engineering
10.000 tpy ACH
The project started july 2024
We are ready to support your next coagulant production project—globally.
Designed and developed by Co-Brains